Bordat, Claire; McCullouch, Bob G.; Sinha, Kumares C.; … - 2004
. This project assessed the extent of the problem of cost overruns, time delays, and change orders associated with Indiana … contracts experience time delays, and the average delay per contract was 115 days. With regard to change orders, the study found … that the dominant category of reasons for change orders is “errors and omissions”, a finding which is suggestive of …