Cost overrun is ubiquitous in public procurement. We argue that this can be the result of a constraint optimal award procedure when the procurer cannot commit not to renegotiate. If cost differences are more pronounced for more complex designs, it is optimal to fix a simple design ex ante and to...
Persistent link: https://www.econbiz.de/10012993698
For the procurement of complex goods the early exchange of information is important to avoid costly renegotiation ex post. We show that this is achieved by bilateral negotiations but not by auctions. Negotiations strictly outperforms auctions if sellers are likely to have superior information...
Persistent link: https://www.econbiz.de/10013024680