This paper gives an overview of good and bad practice for understanding and curbing cost overrun in large capital investment projects, with a critique of Love and Ahiaga-Dagbui (2018) as point of departure. Good practice entails: (a) Consistent definition and measurement of overrun; in contrast...
Persistent link: https://www.econbiz.de/10012911309
Project promoters, forecasters, and managers sometimes object to two things in measuring inaccuracy in travel demand forecasting: (1) using the forecast made at the time of making the decision to build as the basis for measuring inaccuracy and (2) using traffic during the first year of...