Golenko-Ginzburg, Dimitri; Gonik, Aharon; Laslo, Zohar - In: Mathematics and Computers in Simulation (MATCOM) 63 (2003) 2, pp. 105-117
The paper presents a heuristic for resource constrained network project scheduling. A network project comprising both alternative deterministic decision nodes and alternative branching nodes with probabilistic outcomes is considered. Several renewable activity related resources, such as machines...